|

|
Vanguard Installs Injection Moulder
Vanguard,
leading rigging and heavy lifting specialist, has completed a project for
Grinaker-LTA Civil Engineering. This project, commissioned by an air navigation
service provider, involved the construction of a new radar tower to serve East
London Airport.
Heavy rigging specialist, Vanguard, has employed its innovative lifting methods
to install an injection moulder at Toyota’s Durban resin factory. This is one of
the many jobs completed for the car manufacturer.
A full rigging study was completed before the project began to determine the
exact logistics involved in the project. One of the challenges of the project
involved bringing in the heavy equipment, rotating it and lowering it into
position. This involved working in a confined space around the existing
equipment.
According to James Robinson, project engineer, Vanguard, Toyota initially wanted
to remove one of the factory walls so that the moulder could be installed.
“After we completed the rigging study, we determined that we could in fact
co-ordinate our efforts in such a way that we could complete the job without any
major disruption.”
The injection moulder used for manufacturing bumpers, consists of three heavy
components namely a 50t base and two 60t side brackets, as well as auxiliary
hydraulic parts. A gantry system was utilised to offload the equipment and place
into position. Vanguard also employed its rotating hook and jack and slide
system to ensure the efficient and accurate moving of the components.
The precision with which the base was levelled and lifted ensured that once in
place, no further adjustments were necessary, thus saving time.
“After the base was lowered into final position and set onto bolts, the side
frames were installed using the gantry system. The auxiliary hydraulic equipment
was craned into the factory as needed in the installation process ensuring the
optimum usage of the space available,” says Robinson.
The job was finished on schedule with the installation of the heaviest
components taking approximately five days while the rest of the mechanical and
electrical work took a further three weeks.
 |