|

|
Vanguard Transforms Moving Task
With Latest Technology
South
Africa’s leading global heavy lifting and logistics
specialist, Vanguard, has recently completed two heavy lift
projects involving two 252 ton stators. A total of six
stators are due to be delivered. Four have been shipped to
the Richards Bay Harbour so far and two of these stators
have been transported to a power station in Mpumalanga.
The Toshiba stators were imported from Japan and destined
for the power station, arriving in Richards Bay one year
apart.
The first project completed at the end of 2004 saw Vanguard
moving the nine metre long, six metre high, three and a half
metre wide stator across the wharf to a storage area. It was
then jacked up 1m and loaded onto a beam trailer that
carried the heavy load inland.
While it took two days to move the stator 40m using a jack
and slide system designed by Vanguard, the company managed
to reduce jacking time by almost 50% through the first-time
use in South Africa of self-climbing jacks. When compared to
traditional lifting tasks of this size and nature, the use
of self-climbing jacks shortened jacking time by
approximately one day.
“Having designed 6 rail sections with steel supports to
spread the load, we created a quick-coupling attachment at
the end of each piece to allow a leap-frogging action that
further sped up the operation,” explains Vanguard General
Manager, Andrew Nordengen.
Hydraulic rams with hydraulic clamps were used to push the
load, one of the biggest moved over such a distance in South
Africa to date, using four 100t Hillman rollers with
specially designed heavy-load bearings.
The second project, completed in March this year, saw
Vanguard employing the same equipment, self climbing jacks,
rails, and Hillman rollers, to move the 252t stator.
“This project was slightly different,” says Nordengen. “The
ship docked at the small craft harbour in Richards Bay and
offloaded the stator using its fixed cranes. A thousand
cubic metres of seawater had to be pumped into the ship in
order to keep it stable during off loading.
“The stator was placed onto the rail system that we
positioned next to the ship on the quayside and was moved
40m away from the water. There was a slight incline on the
dock that we had to compensate for by using 22t of
horizontal force to overcome the friction in the rollers and
the actual hill.”
Once
in position, the stator was jacked up one metre onto safety
stands where it will reside until loaded onto a beam trailer
and transported to Mpumalanga.
“We learnt a lot from the first job and completed this move
in one day. I believe we have once again demonstrated our
ability to engineer the fastest, most efficient solution to
extraordinary challenges, even if it entails importing the
latest available technology.
“From what we have learned in our first experiences with the
self-climbing jacks, I am confident that they will greatly
advance our efforts to retain a leading edge in the market,”
concludes Nordengen.
 |