|

|
Vanguard Goes Where No Crane
Has Gone Before
The
investment in a heavy lift strand jack system and the
construction of 62m gantry towers has allowed South African
based company Vanguard to successfully complete the highest
non-crane assisted heavy lift on the African continent, as
part of the US$173 million upgrade and reconstruction of the
Mufulira Copper Mine (MCM) Smelter in Mufulira, Zambia. This
record-breaking feat brings the value of successful turnkey
jobs completed by Vanguard - in sub-Saharan Africa - to over
R41 million, for the year to date.
'Our success in this bid was partly due to our decision to
sub-contract Vanguard to execute this lift,' explains Chris
Du Randt of Murray & Roberts. 'The inclusion of Vanguard’s
new strand jack system was a critical factor in our overall
proposal to the mine, and we believe that this bears
testimony to the enormous value and potential of this smart
solution'.
The project involved the erection of a 49m long, 133t cold
box for the new oxygen plant at the Mufulira smelter. The
cold box column is a single complete unit and therefore
needed to be hoisted up as a single structure. In order to
achieve the required height, the system’s gantry towers were
built up to 62m - the same height as a typical Johannesburg
skyscraper. Vanguard designed and manufactured a hook
specifically for this lift. The 49m cold box was lifted,
rotated 90 degrees and then lowered into its final position.
Although strand-jacking is a known method of hoisting in
other countries - particularly in Europe - it is new to
Africa, and Vanguard’s system is the first of its kind in
South Africa. 'Vanguard is dedicated to being proactive,
particularly within the sub-Saharan context, and this kind
of investment is firmly in line with our policy to offer the
best, most cost-effective solutions to South Africa and the
rest of the African continent,' emphasises Bryan Hodgkinson,
Managing Director Vanguard.
'Our
system is made up of 4 immensely powerful strand jack units
- imported from Hydrospex in Holland - boasting a carrying
capacity of 75 tons each. However, it has a huge potential
capacity, as it can be expanded to include a total of 25
jacks,' states Hodgkinson.
The main benefit of using strand jacks is that of
cost-effectiveness. 'In fact, the only other viable option
was to employ cumbersome, high capacity cranes, which would
have cost more than three times as much, in this case,'
Hodgkinson explains. The gantries are more portable than
cranes as they can be dismantled and transported to remote
areas with ease – most of the equipment being carried in
standard containers. The strand jack units are also
relatively compact and easy to move. In this particular
project, the use of the system offered another unique
advantage – that of convenience. Because it occupies a
comparatively small area, other construction on the site was
able to continue without interruption.
The lifting operation is precisely controlled and
synchronised through a laptop at ground level, via PLC. The
accuracy of control achieved is remarkably within a
deviation of just 1mm. In addition, the software employed
has been specially developed and successfully proven in
heavy lifting operations throughout the world.
It is one thing to invest in sophisticated equipment –
investing in the expertise required to effectively operate
and manage such equipment is a separate issue. To this end,
Vanguard employs a team of qualified engineers, whose
expertise in design, mechanical and structural engineering
is applied to precisely configure the correct solution for
each strand jacking application.
 |