|

|
Vanguard Moves 600 Ton Research Vessel

Vanguard moved the 600t M.V. Ellen Khuzwayo from the
shipbuilder’s warehouse
to the synchrolift at the Cape Town Waterfront
Vanguard, South Africa’s premier
heavy lifting and rigging specialist, has completed a
project using its unique imported Goldhofer trailer system
to transport a newly constructed research vessel, the M.V.
Ellen Khuzwayo, from the shipbuilder’s warehouse to the
synchrolift at the Cape Town Waterfront.
The vessel is named after the late Dr. Ellen Khuzwayo,
teacher, social worker, author and a prominent figure in the
struggle against apartheid.
Built by prominent Cape Town shipbuilder, Farocean Marine
(Pty) Ltd., the vessel was commissioned by a government
department to conduct fishery research. The ship weighs
approximately 600t and can accommodate 23 people. It is
16.5m (five stories) high, 10.2m wide and 43.2m long, and
has taken two years to build.
According to Vanguard’s Managing Director, Bryan Hodgkinson,
the move was successfully completed on 23rd May 2007 using
the company’s Goldhofer modular trailer system.

Vanguard’s imported Goldhofer modular trailer system
transported the ship,
pulled by two Mercedes Titan horses
“This is one of the reasons that
we purchased the Goldhofer trailer system. In addition to
its versatility and modularity, the trailer is incredibly
robust and can be used in a host of applications.”
Vanguard initially imported 24 axles, with a 600t site
capacity, and two Mercedes Titan horses. Following the
successful use of the trailer in various projects, the
company imported a further 12 axles, giving the trailer
system a capacity of over 1000t.
“One of the reasons we chose the Goldhofer is that it offers
virtual axle configuration. We used two 6 axle trailers,
side by side, to transport the heavier stern while the bow
rested on one 12 axle trailer. There was a 15 to 20m gap
between the trailers which was bridged by hydraulic cables.
The virtual axle configuration, set up via computer, enables
the axles to function in the same way as they would if the
middle axles were actually present. Both horses were used to
pull the load on the 4km trip,” says Hodgkinson.
The vessel was constructed in cradles and mounted on
pedestals to ensure a smooth transition onto the trailers.
Once the overhead crane and one of the warehouse walls were
dismantled, the trailers were lowered and manoeuvred beneath
the ship. When in place, the trailer was jacked up and the
move began.
“As far as we know this is the heaviest item to be
transported on a public road in South Africa,” says
Hodgkinson.
The stretch of road from the warehouse to the synchrolift
was cordoned off to ensure safe passage.
 |