|
Vanguard Completes Printing Press Installation

Vanguard has announced the successful completion of a
project for Paarl Web, a division of the Paarl Media Group,
one of the most extensive commercial printing operations in
South Africa. The project involved the heavy lifting and
installation of a MAN Roland 64 page Lithoman IV printing
press. The installation and heavy rigging of the printing
press, the largest of its kind in the country, forms part of
Paarl Web’s expansion and pre-press upgrade project to
fulfil clients’ needs and improve service levels.

The
press consists of various components, including the basic
folder weighing 23,1 tons, double chopper weighing 21,5
tons, angle bar superstructure, folder superstructure, and
the dryer deal part one that weighs 41 tons. According to
Dennis Scholfield, Cape Town Branch Manager, Vanguard, the
scope of the project involved unloading of the cargo through
to actual installation. “Vanguard has extensive experience
in this arena with similar projects completed for printing
companies in Gauteng and Cape Town. “Vanguard discharged
all cargo from Paarl Web’s transporter on-site and unpacked
and prepared the components for installation. Once
everything was in place, we proceeded with the heavy lifting
and positioning of the main components,” says Scholfield.
“The offloading process posed a few challenges as it
occurred on a public road. The craning and positioning of
the components was also challenging due to the space
constraints. However, the use of our hydraulic gantries
ensured that job was completed successfully.” Scholfield
notes that all lifting equipment was certified and compliant
with the Occupational Heath and Safety Act. Access to the
printing hall was gained through a hole in the back wall.
Two 30 ton low bed trucks were positioned against the
temporary access point. Vanguard’s specially designed jack
and roll system was positioned on top of these low bed
trucks. Two 50 ton mobile cranes were positioned adjacent to
the low beds and craned the components from the laydown area
onto the jack and roll system. Once inside the hall, the
components were lifted into final position using 60 ton
hydraulic gantry system and a 30 ton boom truck. “In
addition to the main components, we unpacked and installed
the contents of 15 standard 40 foot containers,” says
Scholfield. Vanguard engineers were also on hand to assist
the technician with the mechanical assembly and
commissioning of the machine.
 |