|

|
Vanguard Completes Large Contract In
Eastern Cape
Vanguard has
completed a contract that involved the construction of
portions of a new particle board plant for leading particle
board and laminate manufacturer, PG Bison, in Ugie in the
Eastern Cape. This is one of South Africa’s largest particle
board plants. The project was awarded in January 2007 and
work began on-site in March.
The scope of work covered the installation of a 150t drying
drum, an energy plant, and the outside area of the plant.
This area includes screw and chain conveyors, walking floor,
debarking system, chipping and flaking line, as well as the
installation of silos.
Vanguard General Manager, Andrew Nordengen says that the
entire project was completed within six and a half months.
“We kept to our schedule and had a host of skilled personnel
on-site such as welders, boiler makers, mechanical fitters,
pipe fitters and engineers. There were certain challenges to
consider, mainly related to the cold weather, but the
project progressed well and the three aspects to the
installation were completed concurrently.”
The drum, used for drying wood chips, was collected from
Durban Harbour in six sections with the heaviest part
weighing 30t. Vanguard offloaded, assembled, lined up and
welded the parts together before lifting the drum and
placing it on trunnion wheels 4m off the ground.
“In order to achieve this we used our 600t and 400t
hydraulic gantries, working in conjunction, to rig the drum
into its final position. The gantry rails were placed on one
metre high stands, while two 13m header beams were placed
one metre above the header plates on top of 15m header
beams. This additional height ensured that we were able to
lift the top of the drum to the required 11,5 metres,” says
Nordengen.

Installation
of a 150t drying drum using 400t and 600t hydraulic gantries
The second component of the project involved the
construction of an energy plant that uses scrap wood and
dust as fuel to create the hot air required in the dryer
drum and to heat the thermal oil for the press. The plant
consists of 500t of equipment, including 100t of structural
steel, 250t of heavy components, and 150t of ducting and
thermal oil piping.

Energy plant – Vanguard completed the construction
comprising 500t of equipment
Nordengen notes that the
construction of the energy plant included the installation
of numerous heavy components, including two 50t stepgrates,
a 21t combustion room, a thermal oil tank weighing 20t, two
economiser units, the heaviest weighing 32.8t, as well as a
35t turbix.

Vanguard utilised its specialised staff and equipment to
install chain conveyors, screw conveyors and a bucket
elevator as part of the plant’s outside area
The last part of the project saw Vanguard installing chain
conveyors, screw conveyors and a bucket elevator. These
components form the outside area of the plant and are used
for moving various materials around the plant. Included in
this outside area was the installation of screens, flakers,
chipper, grinders, shredder, walking floors, debarking line
and log feeder. Vanguard also assembled storage silos that
stand up to 30m high.

24m high, 10t chimney of the energy plant being craned into
position
“Our scope for this portion of the project included the
complete mechanical commissioning, as well as the loading,
transporting, offloading and de-stuffing of containers,”
says Nordengen.
“This task required considerable planning to get the 160
containers and 100 break bulk loads to site in the order
that they were needed and used. At the height of operations
we were de-stuffing 29 containers a day, a task that was
facilitated by our Freight and Transportation Management
division.”
Nordengen concludes that
Vanguard managed 77 people on site, a number that almost
doubled since the project began. “The calibre of skilled
people that were on-site, as well as Vanguard’s host of
specialised equipment, including gantries, cranes, forklifts
and cherry pickers, ensured that the project was
successfully completed within the necessary time frame.”
 |