blue leftSpecialised Lifting and TransportationMechanical and Electrical ConstructionRelocation and InstallationFreight and Transport Management
     


Vanguard Awarded Heavy Transport
Contract By Schenker


The versatility and modularity of Vanguard’s trailer demonstrated on-site

Heavy lifting and rigging company Vanguard has announced the completion of a project for German logistics group Schenker. Vanguard utilised its imported modular trailer to transport cargo in excess of 300 tons from Richards Bay Harbour to two inland sites.

Vanguard transported a ball mill to a new cement plant in Randfontein on the West Rand of Johannesburg, and a kiln to a plant refurbishment project in Lichtenburg in the North West Province.

According to James Robinson, Vanguard project engineer, the two items arrived at Richards Bay Harbour from China. “The cargo arrived in December, a little later than scheduled. This essentially meant that due to the load being classified as abnormal and thus requiring a police escort, we had to wait until the new year because this type of transport is embargoed in December due to the holiday traffic. We needed to come up with an interim solution.”

A 12-axle line trailer was dispatched to Richards Bay where the kiln and ball mill each measuring 18 metres long and 5,5 metres wide, were offloaded from the ship and transported to a temporary storage site within the harbour.

“The versatility of the trailer system came into play here, and allowed us to offload the items onto stands without using cranes or additional equipment. The loads were wider than the trailers which facilitated the placing of the pedestals strategically around the trailer. We then lowered the suspension of the trailer, letting the items rest on the pedestals, before driving the trailer out.”

In January, Vanguard used its modular trailer once again, this time configured in an 18-axle line combination, to transport the kiln and ball mill from the harbour to their respective destinations.

“We lowered the suspension of the trailer system, manoeuvred it beneath the load, raised the suspension and drove off,” says Robinson.

Vanguard moved one load at a time, with the ball mill destined for Randfontein transported first.

Robinson notes that the constant rain made conditions on-site a challenge in Randfontein. “The trailer had to be driven up a muddy road which was fairly steep. In addition, the actual space on site was limited and the ball mill had to be offloaded on a cement plinth while the client readied its final position. There was also not much space around the plinth. At the top of the hill, near the plinth, we used the manual steering capabilities of the trailer to manoeuvre it and offloaded the ball mill without a hitch.”

The trailer was immediately sent back to Richards Bay to collect the second load, the kiln, which was transported to Lichtenburg.

“The modularity and versatility of the trailer assisted us in successfully completing this job. The use of the trailer also ensures that we have the ability to adapt quickly to situations and develop solutions to problems that occur without downtime or incurring more costs,” Robinson concludes.