|

The transformers were transported on
Vanguard’s modular trailer using
three horses
in a pull-pull-push configuration |
Vanguard is currently
completing a turnkey contract to transport 6 x
667MVA single phase power transformers, 15 x 133.3
MVA single phase reactors and accessories
manufactured by Japan AE Power Systems from Richards
Bay Harbour to various sites.
The transformers, each weighing 255 tons with an
additional 60 tons of accessories, and reactors,
each weighing 82 tons, are destined for Eskom
substations in the Free State and Mpumalanga. This
contract was awarded by Sumitomo Corporation, a main
contractor to Eskom.
The electric substation equipment is to be installed
at each 765 kV transmission grid substation which is
supplied with power from multiple coal-fired power
stations in Mpumalanga. The project is being carried
out to upgrade the electricity grid to meet rising
demand for power. |
|
The transformers are single phase units, with one
unit allocated per phase due to South Africa’s
configuration of a three phase electricity system.
The units are purposefully designed and manufactured
to minimise the transport weight.
The project has been underway for two years with
Vanguard’s first step researching and establishing a
viable transport route.
“This included a comprehensive route survey and
bridge analysis to ensure that the weight could be
handled, as well as ensuring there were no overhead
structures along the way,” says James Robinson,
Vanguard project engineer. “We also used a liaison
that managed Telkom and Eskom for us, to ensure that
power and communication lines could be lifted or
lowered accordingly.”
Vanguard designed a trailer specifically to suit the
transport requirements of the project, with the
transformers measuring 10m in length, 4,9m in width
and 5,25 in height. In order to optimise the
trailer, Vanguard had to procure additional
equipment. The trailer is 30m long and 5m wide and
is driven by three 610hp Mercedes Benz horse
tractors in a push-push-pull configuration.
“However, a huge obstacle presented itself just
before the first shipment was due to arrive,” says
Robinson. “The proposed and approved route included
portions of the N2 towards Pongola which was due for
road works as part of an upgrade project. The road
was closed in February and would remain so for the
next two years.
“Working on a deadline we investigated other routes
but nothing suited our purposes. But after some
research and some creative thinking, we opted for a
route through Swaziland.”
The route runs parallel to the N2 and includes a
highway that is relatively new and in good
condition. It also has no bridges which ensured that
Vanguard was able to obtain clearance relatively
quickly.
“There was a lot of additional pre-preparation work
which involved us working with the Swaziland’s
communications company and electricity company to
ensure that the telephone and power lines are not an
issue.”

Vanguard completed the customs clearing and harbour
staging in Richards
Bay harbour when the first transformers arrived
Robinson notes that the company’s extensive
experience in route evaluation, research and similar
transport projects ensured the success of the job
while remaining in line with the delivery deadline.
“Once the first four transformers arrived in
Richards Bay, we handled all the customs clearing
and harbour staging,” says Robinson. “The
transformers are extremely sensitive pieces of
equipment and cannot be bumped or jostled in any
way. We elected to use gantry equipment, which is
safer and lessens the likelihood of bumps and
knocks. We also used a staging trailer within the
harbour which is smaller and more mobile. Once
offloaded, the transformers were stored in a lay
down area. This ensured efficient handling, allowing
us to offload all four in one day.”
The remaining two single phase transformers will be
arriving by December 2009 with the remaining single
phase reactors expected in August and October 2009.
From the harbour, the transformers are being
transported to the various sites where they will be
offloaded and slid into final position. This
involves turning each transformer 90 degrees before
sliding and final alignment. To accomplish this,
Vanguard designed and built a turntable to make the
turning process safe and impact free.
“The offloading is accomplished using a combination
of the turntable, 1000 ton gantry system and jacking
tools. While using gantries in this type of
application is not common practice, especially with
transformers of this size, we established that this
was the best method for the project, as it is safer
and quicker.”
The project is expected to continue for the next
eighteen months, with completion anticipated by
2010.

The transformers are
precisely placed using a hydraulic gantry, before
being rotated 90 degrees on a custom-built turntable
 |