|

Vanguard deployed a large team and a host of
specialised
equipment to site |
Vanguard is currently
completing a large-scale project involving
offloading of cargo, on-site logistics, installation
of equipment, and mechanical installation of
bottling lines for Krones A.G.
Vanguard was awarded the contract by Krones AG, a
German packing and bottling machine manufacturer,
for the completion of a project for the new Sedibeng
Brewery in South Africa.
According to Andrew Nordengen, Vanguard director,
the project comprises four stages. “The first part
of the project consisted of offloading and managing
250 containers on-site for the piping construction
of the brew house. We destuffed the containers and
arranged various items, such as piping lengths,
valves, pumps and fittings onto wooden shelving.
This ensured that the piping contractors were able
to easily find the components they needed and in the
order they needed them.” |
|

The second part of the project saw Vanguard
offloading, rigging and installing tanks weighing
between 3 and 25 tons and measuring up to 15 metres
tall. This also included the assembly of platforms
and a mash filter.
The first and second parts of the project are
complete.
“We’re currently underway with the remaining two
stages. One of our teams is in the process of
installing a malt silo,” says Nordengen.
This includes the structural work, as well as the
installation of the malt handling equipment, such as
chain and screw conveyors, and bucket elevators,
which is needed to transport the malt from the silo
to the brew house.

The large-scale project consists of offloading of
cargo, on-site logistics,
installation of equipment, and mechanical
installation of bottling lines
The final portion of the project sees Vanguard
completing the mechanical rigging and installation
of the bottling lines.
“Vanguard is installing a host of equipment, such as
pasteurizers, labellers, fillers, a washer, and
depalletisers. We are also responsible for the
levelling, positioning and mechanical installation
of all conveyors.”
In addition, the company is offloading and
destuffing 210 containers and 27 break bulk pieces
to be used in the packaging hall.
The project has been underway since February with
Vanguard deploying up to 92 staff members to site,
as well as a host of specialised equipment,
including two mobile cranes, three Ormigs, a boom
truck, a 160 ton crane and a tower crane with 50
metre hook height.
The entire project will be completed by later this
year.
 |